Feature · Production planning
A weekly plan your shop can actually keep.
One click turns every open production order into a week-by-week plan against real machine capacity, planned from live shop-floor progress. Boards show load against capacity per machine, at-risk orders are ranked with the week each one must start, and every data defect that could quietly corrupt the plan is listed before it can.
| Machine | W18 | W19 | W20 | W21 | Note |
|---|---|---|---|---|---|
| Mixer A | 31.5/40 | 38.0/40 | 24.0/40 | 18.5/40 | Headroom |
| Fill line 1 | 34.5/40 | 41.0/40 | 22.0/40 | 27.5/40 | Over in W19 · book overtime or move |
| Pack bench | 20.0/35 | 33.5/35 | 35.0/35 | 12.0/35 | Headroom |
| Mixer B | 12.0/24 | 9.5/24 | 21.0/24 | 6.0/24 | Headroom |
Example layout, demo data from Sable & Oak Beauty · live tool in the product.
How it plans
Real routings. Real machine hours.
The plan is only as honest as its inputs, so the inputs are the ones your shop already has: operation sequences with setup and run times, the machines each step can run on, and the outside processes with their lead times.
Every product that gets made carries a routing: the operations in order, each with a setup time, a run time per unit, and the machines it can run on. Outsourced steps carry a lead time instead of a machine. That is enough to plan a shop, without a consultant and without a Gantt chart nobody maintains.
One click generates a week-by-week plan for every open order against real machine capacity, and it plans the remaining work from shop-floor progress, not the paperwork. Finished operations stay finished; the plan only ever schedules what is genuinely left to do.
Each plan is a deterministic, immutable snapshot with a fingerprint of its inputs. When someone asks why a date moved, the answer is on record, not in someone's head.
The boards
See the load. Catch the late orders early.
Two boards run the week. The capacity board shows load against available hours per machine per week, with overtime and downtime bookable inline. The at-risk board ranks orders by severity and names the week after which no amount of capacity can save the date.
Built in
The details that separate a plan from a wish.
Routings
Setup and run times per operation
Operation sequences with machine affinity and outsourced steps with lead times. The plan works from how the work actually flows.
One click
Replan from shop-floor progress
The plan schedules the remaining work, not the original paperwork. A half-finished run stays half-finished when you replan.
Capacity
Load vs capacity, per machine per week
Weekly buckets against real available hours. Book overtime or downtime inline and the plan absorbs it.
At risk
Must-start dates, ranked by severity
Every order that can still be saved shows the week it must start. Past that week, the board says so, before the customer does.
Pinning
Replans respect your decisions
Pin an operation to a machine and week, and every future replan schedules around it instead of over it.
Exceptions
Bad data surfaces first
Missing run times, impossible dates, orphaned operations: every defect that could silently corrupt a plan, listed worst first.
At a glance
Honest scope, on purpose.
This is weekly rough-cut capacity planning: weekly buckets, linear routings, deterministic replans. It is not a day-level Gantt simulator, and your shop will thank you for that.
Buckets
Weekly
Rough-cut capacity, not day-level Gantt.
Replan
One click
From live shop-floor progress.
At-risk board
Ranked
With the must-start week per order.
Every plan
Snapshotted
Immutable, with fingerprinted inputs.
On the roadmap · next
Next up: forecast & subscription netting.
The capacity planner in the launch box answers this week's question. The next layer answers next month's: forecast and subscription demand versus supply, netted per SKU per date.
Gap equation · roadmap
Forecast & subscription netting nets committed orders, subscription replenishments and forecast lines against stock and work-in-progress, then explodes the gap down the BOM tree into suggested runs and purchase orders. It builds on the shipped planner rather than replacing it.
On the roadmap. Waitlist customers shape the order it lands in, see the full roadmap.
Related reading
Go deeper.
- MRP & planning
What is MRP, really? (plain English)
MRP stands for Material Requirements Planning. In practice it answers one question: to fulfil my orders, what do I need to make or buy, in what quantity, and by when. Here is how the maths works.
- MRP & planning
MRP vs ERP: which do you actually need?
MRP plans what to make and buy. ERP runs the whole business. For most small manufacturers the answer is MRP plus the accounting they already use. Here is how to tell them apart and which fits where.
- Bills of materials
How to build a bill of materials (step by step)
A bill of materials is the spine of any production operation. Here is how to build one that captures real-world yield, sub-assemblies, and the operator-friendly detail that keeps the floor running.